Which of the following documents would MOST likely be impacted?

A project manager receives a request for a minor change to one of the deliverables. Which of the
following documents would MOST likely be impacted?

PrepAway - Latest Free Exam Questions & Answers

A.
Work Breakdown Structure (WBS)

B.
Project charter

C.
Communication plan

D.
Quality plan

Explanation: