Which of the following estimates should be given to the project sponsor?

A project manager is two weeks into a project when an unexpected delay occurs. Material that is
needed to complete the project could be available in three business days; however, the project
team believes that estimate is unrealistic and that it will take five business days for the material to
arrive. The project manager was informed by another employee in the material company that it
could take up to thirteen days to receive the materials. Which of the following estimates should be
given to the project sponsor?

PrepAway - Latest Free Exam Questions & Answers

A.
5 business days

B.
6 business days

C.
8 business days

D.
13 business days

Explanation: