PrepAway - Latest Free Exam Questions & Answers

Tag: Exam PMI-SP

Exam PMI-SP: PMI Scheduling Professional

What project management process are you working with when you create a new target schedule?

You work as a project manager for BlueWell Inc. Some of the activities in your project are not
being completed on time. You review these activities with your project team discovered that the
time estimates for the project are much more aggressive than what they are actually experiencing
in the completion of the activities. You decide on to create a new schedule for the project. What
project management process are you working with when you create a new target schedule?

Which one of the following is NOT an input to the Develop Schedule process?

You are the project manager for your organization. You and the project team are developing the
project schedule for your current project. In addition to the enterprise environment factors and the
organizational process assets, you will need seven other inputs to this process. Which one of the
following is NOT an input to the Develop Schedule process?

what type of resource for this project?

You are the project manager of the NHQ project. This project deals with a new technology that
your company has never used before. You have petitioned the management to hire a consultant to
help you and the project team to create the WBS, the activity list, and complete the duration
estimates. The management is concerned about the costs of the consultant, but agrees to your
request because of the nature of this new work. The consultant can best be described as what
type of resource for this project?

What is this limit technically called?

Holly is the project manager for her organization. In her project, she has worked with the project
team to define when the project team will be utilized in the project, the duration of the project
activities, and the sequence in which the project work must be completed. During several phases
of her project, the project team will need to work more than fifty hours per week. The project team
members have agreed this is necessary and they’re willing to do the work to complete the project.
Management, however, has not approved Holly’s schedule based on the overtime the scheduling
will require. They have set a limit on the project schedule of 45 hours per week. What is this limit
technically called? Each correct answer represents a complete solution. Choose all that apply.

What value do you report?

You are the project manager of a project that has a budget of $675,000 and you have completed
40 percent of the project work. Your project is supposed to be 60 percent complete but you are
actually only 40 percent complete. Due to some errors, however, you have actually spent
$335,000 of the budget. Management wants to know what the project’s cost performance index
(CPI) is. What value do you report?


Page 8 of 31« First...678910...2030...Last »