Which statement regarding a project’s outputs, outcomes and benefits is true?

A.
All outputs have tangible benefits
B.
Outcomes are the longer term results from realizing business benefits
C.
Outputs are derived from using the project’s products
D.
Benefits are measurable improvements resulting from the project’s outcomes
I agree with the answer. D