Which is a specific objective of the Starting Up a Project process?
A.
To establish how the project’s products will be delivered and at what cost
B.
Ensure there is a common understanding of the benefits expected from the project
C.
To ensure there is business justification for initiating the project?
D.
To approve the Plan for the next Stage
I agree with the answer. C