The Project Board have overall control at what level?
A.
Day-to-day control for a management stage within stage tolerance
B.
Work Package level within Work Package tolerance
C.
Project level within project tolerance
D.
All levels of plans and tolerances
C
0
0
should’t it be with the stage level with the stage tolerance
2
0