The Project Board will allocate tolerances [ ?

Identify the missing words in the following sentence. The Project Board will allocate tolerances [ ? ]
to the Project Manager.

PrepAway - Latest Free Exam Questions & Answers

A.
for each Work Package

B.
for the project

C.
for each management stage

D.
for each technical stage

9 Comments on “The Project Board will allocate tolerances [ ?

  1. Rodrigo says:

    A, the answer given is correct.

    This is because Corporate or Programme management defines the overall project tolerances w/in which the PB must work, and in order to do this effectively the PB defines the overall Work Package tolerances w/in which the PM must conduct management and control activities.




    0



    2
  2. Sharifi says:

    “C” is the answer:
    The Project Board has overall control at a project level, as long as forecasts remain within project tolerance, and will allocate tolerances for each management stage to the Project Manager. “Sharifi”