Which statement is an appropriate entry for the Initiation Stage Plan?

A.
The Daily Log has been updated with the new risks which were identified while preparing the
Initiation Stage Plan.
B. initiation stage.
The plan is based on the external outsourcing consultants being available at the start of the
C.
The initial project cost estimate of £2.5m, will have a tolerance of +£125k J•£75k.
D.
The project management team will consist of representatives from the IT and Facilities
Divisions.