Which 2 actions should the Team Manager take in response to this situation?

The chair of a quality review meeting advised the Team Manager that, because there were so
many major issues, the product had been rejected. The presenter estimated that the corrections
would take about two weeks. The re-assessment of the product will take a further week, resulting
in a three-week delay. The Work Package only has one week tolerance.
Which 2 actions should the Team Manager take in response to this situation?

PrepAway - Latest Free Exam Questions & Answers

A.
Ask the reviewers to work overtime to prevent the delay.

B.
Ensure that the situation is included in the next Highlight Report.

C.
Raise an issue explaining that tolerances are forecast to be exceeded.

D.
Advise the Project Manager of the risk that there may be a two-week delay in the delivery of
one of the products.

E.
Ensure that the Quality Register is updated with the quality review result.