2 Comments on “If Project tolerances were threatened, who needs to be notified?

  1. Tn Trichy says:

    Book: PRINCE2 Revealed: Including how to Use PRINCE2 for Small Projects

    Extract: If project tolerances are threatened, the project board executive must escalate to senior management.

    who needs to be notified? —> Corporate or Programme Management