Which statement describes risk cause?

A.
The impact of a risk on the stage and project tolerance
B.
The situation or event that gave rise to a risk
C.
The area of uncertainty in terms of the threat or opportunity
D.
How likely a risk is to occur in a given project situation
Ok
Risk cause describes the source of the risk
Risk event describes the area of uncertainty (threat or the opportunity)
Risk effect describe the impact
0
0