Which role has a specific responsibility for referring to the Project Board if any delegated limits of
authority or allocated change budget are forecast to be exceeded?

A.
Team Manager
B.
Project Assurance
C.
Change Authority
D.
Project Manager
You must be logged in to post a comment.
C
0