If, at the end of each stage, circumstances external to the project had changed which affect the
project’s costs, risks and benefits, which product should be updated to reflect this?

A.
Exception Plan
B.
Project Plan
C.
Project Brief
D.
Business Case
Answer is D.
0
0
i agree
0
0
I agree with the answer. B
0
0
according to the mock exams its the business case
0
0
The purpose of the Business Case is to set out the justification for the project.If the circumstances have changed, Business case must be updated for continued business justification. Later Project Plan can be updated accordingly or replaced with Exception Plan.
So the answer should be D.
Please anyone have idea, suggest.