If a Project Manager were to receive progress information on a Work Package during a stage,
which one of the following products would the Project Manager update to show the progress that’s
been made?

A.
Checkpoint Report
B.
Stage Plan
C.
Benefits Review Plan
D.
Project Plan
Correct answer is B