Which of the following would be carried out during the Starting Up a Project process?

A.
Establish the procedure for identifying and managing risks during the project
B.
Create a detailed Business Case
C.
Appoint individuals to carry out the work required in project initiation
D.
Ensure that plans for realizing the post-project benefits are managed and reviewed
C