Which of the following would be carried out as part of a post-project benefits review?

A.
An assessment of whether the project fulfilled its original objectives
B.
A review of the performance of the project’s products in operational use and identification of
whether there have been any side-effects
C.
An assessment of the project’s risk management procedure
D.
A review of the performance of the project management method and the project management
team
Ok
B.
A review of the performance of the project’s products in operational use and identification of
whether there have been any side-effects (beneficial or adverse)