Which of the following tasks is the first to be performed on receipt of a new issue?

A.
Assess its impact on the project’s objectives
B.
Determine whether the issue is a request for change, off-specification or a problem/concern
C.
Escalate if it is beyond the delegated authority
D.
Identify options to resolve the issue and submit a recommendation
I have the same idea. B