which of the following products would first be sent to the Project Board to inform them of this deviation?

If any type of issue or risk (or aggregation of them) cannot be resolved within the tolerances set by
the Project Board, which of the following products would first be sent to the Project Board to inform
them of this deviation?

PrepAway - Latest Free Exam Questions & Answers

A.
Exception Report

B.
End Stage Report

C.
Highlight Report

D.
Updated Risk and Issue Registers