Which of the following is NOT established as part of the pre-project work?

A.
A Plan for the work of initiation
B.
Information on the various ways the project can be delivered
C.
A description of what the project is to deliver
D.
A plan for how and when a measurement of the achievement of the project’s benefits can be
made
I have the same idea. D