Which of the following is FALSE regarding an Exception Report?

A.
It describes a forecast deviation of stage or project level tolerance
B.
It contains recovery options and a recommendation
C.
It replaces a Stage Plan or Project Plan
D.
It describes the consequences of the deviation
I agree with the answer. C