Which of the following is carried out as part of the Initiating a Project process?

A.
Ensure there is authority to deliver the project’s products
B.
Ensure there is a common understanding of the reasons for doing the project
C.
Appoint the Executive and Project Manager
D.
Create a stage Plan for the next stage of the project
I choose B