Which of the following is a concession?

A.
When a product fails to meet its quality criteria
B.
When an off-specification is raised by the Senior User
C.
When an off-specification is accepted by the Project Board or Change Authority without
immediate corrective action
D.
When a known error is no longer a problem
C