Which of the following does PRINCE2 say are typical characteristics of a Project Board member?

A.
Democratic, supportive, can make decisions
B.
Hard working, experienced, forceful
C.
Focused, steadfast, autocratic
D.
Have authority, credibility, ability to delegate, available when required
Correct answer is D.
1
0
i agree
0
0
“D” is the right answer:
A good Project Board should display four key characteristics: page 34
• Authority
• Credibility
• Ability to delegate
• Availability
1
0
C
0
1
It is clearly written in Book,
PRINCE2 talks about an effective Project Board displaying four key characteristics: authority,
credibility, an ability to delegate, and availability
The correct answer is D.
1
0
From the manual
PRINCE2 says that a Project Board should have 4 characteristics. These characteristics are:
• Authority so they can get things done
• Credibility
• Ability to delegate
• Availability, especially to support the Project Manager
0
0
D
0
0