Which of the following describes risk proximity?

A.
The timeframe over which the risk mitigation actions should be implemented
B.
The schedule for the risk management activities related to a plan
C.
The timeframe over which a risk will be monitored by the risk owner
D.
The timeframe for when the risk might materialize