Which is NOT an objective of PRINCE2 stages?

A.
Provide an opportunity to assess the project viability
B.
Identify the necessary Work Packages
C.
Allow clarification of the impact of an external influence
D.
Ensure that key decisions are made prior to work needed to implement them
I agree with the answer. B