Which is an aim of the Starting up a Project process?

A.
Understand how and when the project’s products will be delivered and at what cost
B.
Ensure that there is authority to deliver the project’s products
C.
Do the minimum necessary in order to decide whether it is worthwhile to even initiate the
project
D.
Create the set of management products required to control the project
Wrong answer
0
0
Answer is C.
0
0
i agree
0
0
The answer given is the correct one. Understanding how and when the project’s products will be delivered and at what cost is part of the feasibility and viability analysis which goes into forming the documented and agreed business case of the project during the Startup Process.
0
0
“C” is the correct answer.
0
0
Correct answer is C
See “Managing successful projects with PRINCE2”
page 121, section 12.1 Purpose
“…
The aim is to do the minimum necessary in order to
decide whether it is worthwhile to even initiate the
project.”
0
0
c
0
0
C is the correct answer.
0
0
The correct answer should be C.