Which is a specific responsibility of Project Assurance?

A.
Approving the Risk Management Strategy
B.
Giving ad-hoc direction to the Project Manager
C.
Reporting highlights to the Project Board
D.
Checking the right people are being involved in writing product descriptions
I agree with the answer. D