Which is a purpose of the Directing a Project process?

A.
Enable the Project Board to exercise overall control of a project
B.
Prepare a solid foundation for the project
C.
Establish the prerequisites for the initiation of a project
D.
Assign Work Packages
I agree with the answer. A