Which is a purpose of a Project Brief?

A.
Define how and when a measurement of the achievement of the project’s benefits can be made
B.
Define any lessons from previous projects and how they may affect this project
C.
Communicate the quality techniques and standards to be applied to achieve the required
quality levels
D.
Provide sufficient information for the decision on whether to initiate the project
I have the same idea. D