When does the Directing a Project process start?

A.
On completion of the Starting up a Project process
B.
On completion of the Initiating a Project process
C.
When the Starting up a Project process commences
D.
After the project has been authorized
This is wrong – correct answer is A
See page 135 of the PRINCE2 manual, section 13.3
1
0
i agree
0
0
The correct Answer is A:
See page 135 of the PRINCE2 manual, section 13.3, as suggested by “PRINCE2 student,” or reference page 18 of PRINCE2 for Dummies.
0
0
I agree completely to Mr Rodrego, it is true
0
0
Correct answer is A
See “Managing successful projects with PRINCE2”
Page 135, section 13.3
The Directing a Project process starts on completion
of the Starting up a Project process and is triggered
by the request to initiate a project.