When does the Directing a Project process begin?

A.
When corporate or programme management have issued a project mandate to trigger a project
B.
As soon as the necessary authorities have been appointed for initiating the project
C.
On completion of the Starting Up a Project process
D.
Once the Project Initiation Documentation had been submitted for Project Board approval
Correct answer is C