What is the goal of the ‘Identify context’ step within the recommended risk management
procedure?

A.
Identify responses to risks identified in the Business Case
B.
Understand the specific objectives that are at risk
C.
Gather information about risks for inclusion in Highlight Reports to the Project Board
D.
Identify the threats and opportunities that may affect the project’s objectives
B is correct