What is a purpose of the Initiating a Project process?

A.
Delegate day-to-day management of the project to the Project Manager
B.
Answer the question: do we have a viable and worthwhile project?
C.
Understand the work that needs to be done to deliver the project’s products before committing
to a significant spend
D.
Enable the Project Board to be provided with sufficient information so that it can review the
success of the current stage
I agree with the answer. C