What is a purpose of the Closing a Project process?

A.
Provide a fixed point at which acceptance for the project product is confirmed
B.
Enable the Project Board to review the success of the current stage
C.
Assign work to be done and monitor such work
D.
Enable the organization to understand the work that needs to be done to deliver the project’s
products
I have the same idea. A