If, for whatever reason, the business justification disappears once the project is underway, what
does PRINCE2 suggest should happen?

A.
The project should continue until the next end stage assessment
B.
A benefits review should be undertaken
C.
The project should be stopped or changed
D.
An exception assessment should be held to approve an Exception Plan to recover from the
situation