The Manage by Exception principle sets tolerances for six areas of the project, Time. Cost and
Quality are three of them, what are the other three?

A.
Scope, People & Resources, Benefit
B.
Scope, Risk, Product
C.
Risk, Benefit, Product
D.
Scope, Risk, Benefit
Correct answer: e. Scope, risk, benefit