Once a product has been completed, from who would the Team Manager get approval for its
completion?

A.
Project Manager
B.
The authority defined in the quality responsibilities section of the product’s Product Description
C.
Quality Assurance as part of their independent audits
D.
Project Support
I agree with the answer. B