Identify the missing words in the following sentence. If the Project Manager needs to know the
results of a quality review, the [ ? ] will provide a summary together with the date of any follow-up
meeting.

A.
Stage Plan
B.
Issue Register
C.
Daily Log
D.
Quality Register
Explanation:
Reference:http://www.prince2primer.com/prince2-quality-theme/
I have the same idea. D