During project initiation, who determines the use of a Change Authority and whether a change
budget will be used?

A.
Project Board
B.
Change Authority
C.
Project Manager
D.
Corporate or Programme Management
You must be logged in to post a comment.
Answer is A.
1
0
i agree
0
0
“A” is correct;
The Project Board may also delegate decisions regarding changes to a Change Authority. PB decide whether to use a Change Authority and, if so, agree the level of authority to be delegated, page 267(C.1.1 General responsibilities)
0
0
I have the same idea. B
0
0
please revise your concepts.
0
0
So Change Authority decides on the use of… Change Authority? Too tautological man…
0
0
“A” is correct
0
0
A is correct. Project Board rules.
0
0