Team Plans and the use of seperate people as Team Managers are optional in PRINCE2)
Please refer to section 10.3.2.1 in the PRINCE2 Manual. (Exception Plans are only produced if
requested by the Project Board. Team Plans and the use of seperate people as Team Managers
are optional in PRINCE2)
which process would the stage tolerances be set?
During which process would the stage tolerances be set?
what level?
The Project Board have overall control at what level?
Which of the following is not a factor to consider when determining the length of a stage?
Which of the following is not a factor to consider when determining the length of a stage?
What name is given to the permissible deviation allowed above and below a plan’s target for time and cos
What name is given to the permissible deviation allowed above and below a plan’s target for time
and cost without escalating the deviation to the next level of management?
Which statement is TRUE with regard to technical stages?
Which statement is TRUE with regard to technical stages?
which of the following products would first be sent to the Project Board to inform them of this deviation?
If any type of issue or risk (or aggregation of them) cannot be resolved within the tolerances set by
the Project Board, which of the following products would first be sent to the Project Board to inform
them of this deviation?
which are they?
There are two time driven controls in PRINCE2, which are they?
Which of the following statements are correct regarding tolerance?
Tolerance forms a key element of allowing the Project Board to manage by exception. Which of
the following statements are correct regarding tolerance?
1. The Project Board sets project tolerances
2. Tolerances can be applied for Time, Cost, Scope, Quality, Benefit and Risk
3. The Project Manager sets Work Package tolerance
4. Cost tolerance should not be used to pay for authorized requests for change
Who is responsible for confirming stage and project progress against agreed tolerances?
Who is responsible for confirming stage and project progress against agreed tolerances?