Are the following statements regarding the Starting Up a Project process true or false? 1. How the
project will achieve the required quality will be established 2. How the corporate (or programme’s)
project management method will be tailored to suit the project will be defined

A.
Only 1 is true
B.
Only 2 is true
C.
Both 1 and 2 are true
D.
Both 1 and 2 are false
Correct answer is D