Are the following statements regarding raising exceptions true or false?
1. If the stage is forecast to exceed its tolerances, the Project Manager should produce an Issue
Report to capture and analyze the details of the deviation
2. Where a Work Package is forecast to exceed its tolerances, the Project Manager may request
the Team Manager to produce an Exception Plan

A.
Only 1 is true
B.
Only 2 is true
C.
Both 1 and 2 are true
D.
Both 1 and 2 are false
I choose A