Identify the missing words in the following sentence… A principle of PRINCE2 is that a project has
defined and agreed?

A.
Roles and responsibilities
B.
Specialist teams with appropriate technical skills
C.
Management jobs with job descriptions
D.
Senior managers at all levels of the project management team