The creation of an Exception Plan often follows which situation?

A.
A time or cost slippage occurs during a management stage
B.
An Exception Report being submitted to the Project Board
C.
A Stage Plan is updated due to an urgent corrective action being taken
D.
An Issue Report being created
Correct answer is B
0
0
Answer B is not fully satisfied,
without any reasons why to submit exception report to the management regularly
Why not option A can be an answer.
0
0