You need to ensure that the new teams minimize collisions and maximize release flexibility

You are a scrum master.
You are planning a large product development project that will involve more than 15 team members. You want
to divide the team members into multiple scrum teams.
You need to ensure that the new teams minimize collisions and maximize release flexibility.
What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Create teams that will target different features.

B.
Create teams based on team members’ positions.

C.
Create teams based on technology type.

D.
Create teams by team members’ experience with theScrum process framework.