PrepAway - Latest Free Exam Questions & Answers

You need to determine the process to obtain the most accurate estimates for each user story in your product ba

Your development team uses the Microsoft Solution Framework (MSF) for Agile Software Development 6.0
process template.
You need to determine the process to obtain the most accurate estimates for each user story in your product
backlog.
What should you do?

PrepAway - Latest Free Exam Questions & Answers

A.
Have the development team estimate and use the longest estimates.

B.
Ask the product owner to provide the estimates.

C.
Ask the scrum master to provide estimates.

D.
Have the development team estimate until team members reach consensus.


Leave a Reply