PrepAway - Latest Free Exam Questions & Answers

Which three actions should you perform?

Your development team uses the Microsoft Visual Studio Scrum 2.0 process template. The team has identified
items from the product backlog for the next sprint.
You need to ensure that the team has adequate capacity to complete the next sprint.
Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)

PrepAway - Latest Free Exam Questions & Answers

A.
Review the sprint Burndown chart.

B.
Have the team assign hour estimates to each sprint task.

C.
Review the sprint backlog.

D.
Assign story points to each item in the product backlog.

E.
Review the product backlog with forecast set to On to determine if the sprint can be completed basedon
the team’s velocity.

F.
Set each team member’s per day capacity.

3 Comments on “Which three actions should you perform?


Leave a Reply