Which six actions should you perform in sequence?

DRAG DROP
Your company is deploying a third-party application named App1 by using Microsoft Application
Visualization (App-V) 4.6. App-V 4.6 SP1 has not been installed in the environment. All App-V
deployments must conserve memory when possible. You need to sequence the application for
deployment. Which six actions should you perform in sequence? (To answer, move the appropriate
actions from the list of actions to the answer area and arrange them in the correct order.

PrepAway - Latest Free Exam Questions & Answers

Answer:

Explanation:

Box 1: Create a package
Box 2: Select Rebase DLLs
(this is in advanced options in the wizard)
Box 3: Create a folder named App1 and click Begin Monitoring
Box 4: Install the third-party application
Box 5: Click Stop Monitoring
Box 6: Save the package
Note:
Sample Sequencing This section describes some of the key points to remember during sequencing.
To begin open the Application Virtualization Sequencer and select Create a Package from the
Welcome Screen.
1. Welcome Screen

2. Package Information
3. Advanced Options
When advanced options are selected in the package information screen, the Sequencer will be
presented with options for Microsoft Update and Rebasing DLLs.

4. Monitor Installation After the package information has been collected, the next step is to monitor
the installation of the application. Selecting Begin Monitoring will prompt for an installation
directory. Next, the virtual environment will be built and the Sequencer will start monitoring specific
locations and processes for activity. In App-V 4.6, one change is that the Monitor Installation page
will not minimize after choosing to Begin Monitoring. After selecting Begin Monitoring, most
operations will be recorded as part of the package, unless a specific exception has been configured
on the Sequencer.

After you click “Begin Monitoring” you will be prompted to create the installation folder. In version
4.2 this was done when you clicked “Stop Monitoring.”

5. Configure Applications
6. Launch Applications
7. Package Deployment

8. Saving the Package
The last step in the process of sequencing is to save the package. Saving the package should be done