which one of the following?

You work as a Project Administrator for Company Inc. Your current project is going to finish within a few days. You would like to keep the information of this project as a project template. If you choose to save the file as a template, you are allowed to clear all of the following project attributes for the template except for which one of the following?

PrepAway - Latest Free Exam Questions & Answers

A.
Resource rates

B.
Resources

C.
Values of all baselines

D.
Actual values

Explanation:
There is no option to clear the resources that have been used in the project that you are saving as a template. You are allowed to clear the following five values:
1.Values of all baselines
2.Actual values
3.Resource rates
4.Fixed costs
5.The information about the tasks that have been published on Project Server

Answer options C, D, and A are incorrect. You can clear the values of all baselines, actual values, and resource rates.
What is a template?
A template is a project that is specially designed to be used more than once. A template has an extension .mpt. A template has special characteristics, one of which is that the template is saved into a special location reserved for templates. A template is useful for creating consistent and repeated activities in a project. Therefore, the user need not have to start the project from scratch.