Which of the following actions should you take?

You work as a Project Manager at ABC.com. You are managing a project using Project Server 2010. You have been instructed to create a Project Server resource for the purpose of tracking the amount of money spent by members of the project team on travel and accommodation expenses. Which of the following actions should you take?

PrepAway - Latest Free Exam Questions & Answers

A.
You should create a cost resource.

B.
You should create a material resource.

C.
You should create a people resource.

D.
You should create an equipment resource.

E.
You should create a generic resource.